STH 89 Reconstruction Project

Posted on: July 25, 2022

[ARCHIVED] STH 89 / Farnham Street Construction Update for July 25, 2022

The reconstruction of Farnham Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.

  • Work last week- 07/18/2022 was done on storm sewer from Avalon to Folsom utilizing 2 crews along with grading for the storm water basin south of Waterloo and for the roadway from Waterloo to Folsom. Water main tie-ins were performed along with asphalt paving driveways and manhole patches. 
  • Work next week- 07/25/2022 involves storm sewer from Avalon to Folsom utilizing 2 crews along with grading for the roadway from Folsom to Avalon. Underground utilities and intersection reconstruction will be done at Park and Farnham.

The intersection of STH 89 & STH 73 - Farnham and Park- will be closed Monday July 25 through Sunday August 7

Farnham Street is currently closed to through traffic from Avalon Road to Park Avenue.