The reconstruction of Farnham Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.
The intersection of STH 89 & STH 73 - Farnham and Park- will be closed Monday July 25 through Sunday August 7
Farnham Street is currently closed to through traffic from Avalon Road to Park Avenue.