STH 89 Reconstruction Project

Posted on: July 18, 2022

[ARCHIVED] STH 89 Reconstruction Update, 7-18-22

The reconstruction of Farnham Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.

  • Work last week- 07/11/2022 was done on water and sewer laterals along with storm sewer from Waterloo to Folsom at Frontage Road. Other work included manhole adjustments to final grade from Folsom to Park, sidewalk removal and grading. 
  • Work next week- 07/18/2022 involves storm sewer from Avalon to Folsom utilizing 2 crews along with grading for the storm water basin south of Waterloo and for the roadway from Waterloo to Folsom. Asphalt paving driveways and manhole patches.

Farnham Street is currently closed to through traffic from Avalon Road to Park Avenue.