STH 89 Reconstruction Project

Posted on: July 8, 2022

[ARCHIVED] STH 89 Reconstruction Update, 7-8-22

The reconstruction of Farnham Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.

  • Work this week- 07/05/2022 was done on water main from Waterloo to Folsom, sewer laterals from Waterloo to Folsom, landscaping and sod restoration from Folsom to Park and manhole adjustments to final grade from Folsom to Park.
  • Work next week- 07/11/2022 involves Sanitary Sewer and water laterals on Frontage Road, 
    grading for storm water basin south of Waterloo and storm sewer from Waterloo to the north.

Farnham Street is currently closed to through traffic from Avalon Road to Park Avenue.