[ARCHIVED] STH 89 Reconstruction Update, 6-27-2022

The reconstruction of Farnham Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.

  • Last week, 6-20-22, work consisted of sanitary sewer from Avalon Road to Folsom Street along with roadway aggregate shaping for asphalt and concrete sidewalk work.
  • Work this week - 6-27-2022 continues with sanitary sewer from Avalon Road to Folsom Street along with concrete driveways from Park Avenue to Folsom Street. Additionally, water main work from Waterloo to Folsom and lawn restoration shaping will be done. Asphalt paving from Park Avenue to Folsom Street will take place all day, Monday June, 27th.

Farnham Street is currently closed to through traffic from Avalon Road to Park Avenue.