News Flash Home
The original item was published from 6/20/2022 8:51:50 AM to 6/27/2022 12:00:08 AM.

News Flash

STH 89 Reconstruction Project

Posted on: June 20, 2022

[ARCHIVED] STH 89 Reconstruction Update, 6-20-22

The reconstruction of Farnham Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.

Last week, 6-13-22, work consisted of sanitary sewer from Avalon Road to Folsom Street along with rock blasting for sanitary sewer near Waterloo Street.

Work this week - 6-20-2022 continues with sanitary sewer from Avalon Road to Folsom Street along with concrete curb and gutter and sidewalk from Park Avenue to Folsom Street. Additionally, aggregate placement for asphalt pavement will be started.

Farnham Street is currently closed to through traffic from Avalon Road to Park Avenue.

Additional Info...
Facebook Twitter Email