STH 89 Reconstruction Project

Posted on: May 27, 2022

[ARCHIVED] STH 89 Reconstruction Update, 5-27-22

The reconstruction of Farnham Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.

 Work this week- 05/23/2022

  • Close Farnham Street to thru traffic for Stage 2- Avalon Road to Park Street.
  • Sanitary Sewer Main and services between Waterloo Street and Folsom Street
  • Storm Sewer between Waterloo Street and Folsom Street 
  • Concrete end wall construction at 2nd Ward Creek
  • Roadway grading between Folsom and 2nd Ward Creek

Work next week- 05/30/2022

  • Sanitary Sewer from Waterloo Street to Folsom Street 
  • Storm Sewer between Waterloo Street and Folsom Street 
  • Concrete end wall construction at 2nd Ward Creek 
  • Roadway grading between Waterloo Street and Folsom Street

 Traffic impacts

  • Farnham Street is currently closed to through traffic from Avalon Road to Park Avenue.