STH 89 Reconstruction Project

Posted on: April 29, 2022

[ARCHIVED] STH 89 / Farnham Street Construction Update for April 29, 2022

The reconstruction of Main Street includes grading, select crushed material, base aggregate dense, asphalt pavement, concrete curb and gutter, concrete sidewalk, storm sewer, permanent signing, pavement marking, street lighting, sanitary sewer main and services, water main and services, and all incidental items. The work is scheduled for completion in August 2022.

  • The week of 4-25-22 involved work for the water main north of Poet Street, the sanitary sewer main between Poet Street and Park Street, and the storm sewer between Poet Street and Park Street.
  • The week of 5-2-22 will involve work for the sanitary sewer laterals, water services, and storm sewer between Poet Street and Park Street,  Additionally, work involving culvert pipe removal and replacement at 2nd Ward Creek will take place as well.

Farnham Street is currently closed to through traffic from Folsom Street to Park Avenue.