[ARCHIVED] 2018 Columbus Roadwork Update and Schedule


The City of Columbus current active Road Projects, 2018 (schedule and update):

DOT PROJECT: Hwy 16/60 work under the 151 overpass:  Project currently underway - new pavement, sidewalks, and lighting.  Resurface of all the on/off ramps.  Traffic signals at the off ramps coming from the south only.  Thru traffic in project area maintained throughout.  Expected Completion:  End of AUGUST.


DOT PROJECT: Road Resurface, Park Avenue (Faith Drive to Heritage Way):  new pavement.  Expected start: MAY 7th, Expected Completion: early JUNE. 


CITY PROJECT: S. Water (from E. James to E. School) & E. School (from Park Avenue to Waterloo):  full reconstruction, pavement, water, sewer, storm sewer, sidewalks.  

Expected Start: JUNE 1.  Expected Completion: end of AUGUST.