▼Hibbard Street Construction
22 Alerts
November 11, 2020 2:26 PM
Binder coat is being placed on the sound end of Hibbard and Turner St today, with blacktopping to take place Thursday, Nov. 12.
November 10, 2020 7:39 AM
Due to the weather, the blacktopping on the south end of Hibbard St. has been pushed back to Wednesday, November 11.
November 9, 2020 2:58 PM
Blacktopping to take place on the south end of Hibbard St. on Tuesday, November 10, weather depending.
November 6, 2020 7:31 AM
Grading will take place Saturday on the south end of Hibbard in preparation for blacktopping next week.
November 2, 2020 3:26 PM
All trash and recycling pick up on Hibbard St. has been moved to Wednesday, November 4. There will be NO TUESDAY November 3 trash or recycling pick up. This will allow the concrete driveway aprons and sidewalks to dry before anyone walks or rolls their...
Read On...
October 28, 2020 12:03 PM
Curb and gutter are being poured this week on the south end of Hibbard St., and prepping for asphalt will begin soon.
October 22, 2020 8:16 AM
Rain has put this on hold until the week of October 26.
October 16, 2020 11:20 AM
DPW will have a truck parked on Hibbard to collect your leaves and grass clippings.
October 9, 2020 9:41 AM
Curbs and gutters done, blacktop coming soon!
October 2, 2020 10:52 AM
Update on leaf pickup for Hibbard Street
September 30, 2020 2:28 PM
Hibbard & Turner St. Utililty Improvements
September 25, 2020 11:11 AM
Weekly update
September 17, 2020 4:41 PM
Water Main is complete!
September 2, 2020 1:53 PM
Water Main is halfway complete!
August 27, 2020 7:53 AM
Hibbard St. Reconstruct Weekly Update
August 20, 2020 8:09 AM
Hibbard St. Reconstruct Weekly Update
August 14, 2020 9:38 AM
Hibbard Street Construction is Underway!
July 24, 2020 2:41 PM
August start date is on track.
June 4, 2020 8:14 AM
Latest update on Hibbard Street Reconstruction Project
March 24, 2020 12:42 PM
Update on Utility companies working on Hibbard Street & COVID-19 and how the Governors most recent order affects the project.
February 28, 2020 2:47 PM
Private Sewer Lateral Replacement Program
The City Council has approved the private sewer lateral replacement program for Columbus Residents. The purpose of this program is to work towards reducing inflow and infiltration of clear waters into the sanitary...
Read On...
February 7, 2020 7:41 AM
The public hearing for Hibbard Street Special Assessments will be held on March 10, 2020 at 6:30 PM in the Council Chambers. Bid openings for this project will take place on February 19 and assessments will be sent out on February 20th.
Latest Update:
February 23, 2020 5:30 PM
NOTICE FOR PUBLIC HEARING FOR 2020 PRELIMINARY ASSESSMENTS FOR HIBBARD AND TURNER STREET & UTILITY IMPROVEMENT